exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 408 discussion

Actual exam question from PMI's PMI-RMP
Question #: 408
Topic #: 1
[All PMI-RMP Questions]

A project team will receive a bonus if a project is completed earlier per the contract. However, the cost of early completion will be too high if more resources are added. The risk manager recommends motivating the project team with a slight salary increase instead of contracting more workers for early completion.

Which risk response strategy is the risk manager using in this scenario?

  • A. Mitigate
  • B. Enhance
  • C. Transfer
  • D. Escalate
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 4 days ago
Selected Answer: B
In this scenario, the risk manager is enhancing the chances of achieving early completion by providing a motivational incentive (a slight salary increase) to the existing project team instead of increasing the number of resources. The idea is to increase the likelihood of early completion without incurring the high costs of adding more workers, which could negatively impact the project’s cost efficiency. Enhance is a risk response strategy that focuses on increasing the probability or impact of an opportunity. In this case, the opportunity is completing the project earlier and receiving a bonus. The risk manager is enhancing the chances of early completion by motivating the existing team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago