A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

  • A. Contingency reserves
  • B. Schedule and resource assumptions
  • C. Work breakdown structure (WBS)
  • D. Risk impact matrix
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 5 days ago
Selected Answer: B
The schedule and resource assumptions in the project plan capture the basis for planned durations, resource allocations, and cost estimates. If a project is consistently lagging in CPI and SPI, it indicates issues with how time and resources were initially allocated. The risk manager should review these assumptions to identify discrepancies between the plan and actual performance, then adjust the plan to mitigate further overruns.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago