Exam PMI-RMP topic 1 question 378 discussion

Actual exam question from PMI's PMI-RMP
Question #: 378
Topic #: 1
[All PMI-RMP Questions]

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company, Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

  • A. A request to increase project earnings
  • B. A request to increase project resources
  • C. A challenge to stakeholder thresholds
  • D. A challenge to the project investment
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 5 days ago
Selected Answer: C
The core of the question revolves around influencing the board's acceptance of additional risks tied to Field 2. While there is an investment component, the argument is more about persuading the board to adjust their risk tolerance (thresholds) to accommodate a potentially high-reward opportunity.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago