An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

  • A. Communicate the identified residual risk.
  • B. Implement the risk response plan.
  • C. Assess the identified secondary risk.
  • D. Implement the risk contingency plan.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 5 days ago
Selected Answer: C
The confidentiality risks identified by the contracts department represent a secondary risk—a new risk that arises as a direct result of implementing a risk response, in this case, engaging an external vendor. The risk manager must assess this secondary risk to evaluate its probability, impact, and possible response strategies before proceeding.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago