According to the Standard for Risk Management in Portfolios, Programs and Projects (by PMI) page 32, the risk owner is the individual responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy. It is the responsible of the risk owner to manage the corresponding risk throughout the subsequent risk management processes.
The risk action owner is the person responsible for carrying out the approved risk actions when responding to a given risk; also known as a response owner