The trigger for a highly categorized threat has occurred. The risk has set a response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

  • A. Product Manager
  • B. Risk Owner
  • C. Project Manager
  • D. Risk Action Owner
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 6 days ago
Selected Answer: B
According to the Standard for Risk Management in Portfolios, Programs and Projects (by PMI) page 32, the risk owner is the individual responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy. It is the responsible of the risk owner to manage the corresponding risk throughout the subsequent risk management processes. The risk action owner is the person responsible for carrying out the approved risk actions when responding to a given risk; also known as a response owner
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago