exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 300 discussion

Actual exam question from PMI's PMI-RMP
Question #: 300
Topic #: 1
[All PMI-RMP Questions]

A project manager and risk manager are working on a new hotel development project for their organization and have completed the risk analysis processes for the identified risks. They determined that the organization might not be able to handle the consequences of some of the high-priority risk items, and the project's objectives and designs cannot change. The team is preparing risk responses for these high-priority risks.

Which risk response strategy will effectively manage these high-priority risks?

  • A. Risk mitigation
  • B. Risk avoidance
  • C. Risk escalation
  • D. Risk transference
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
3 weeks, 6 days ago
Selected Answer: D
Transference involves shifting the impact of the risk to a third party, such as through insurance, warranties, or subcontracting to an external entity that is better equipped to manage the risk. Transferring high-priority risks ensures that the organization is not directly burdened with managing consequences it cannot handle effectively.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago