exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 271 discussion

Actual exam question from PMI's PMI-RMP
Question #: 271
Topic #: 1
[All PMI-RMP Questions]

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor’s ask?

  • A. Quantitative risk analysis
  • B. Sensitivity analysis
  • C. Qualitative risk analysis
  • D. Monte Carlo analysis
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
4 weeks ago
Selected Answer: C
To present the risks that have the most impact on achieving project objectives, the risk manager should perform qualitative risk analysis, which prioritizes risks based on their probability of occurrence and impact on project objectives (such as scope, time, cost, or quality). This allows the risk manager to identify and rank the most significant risks to discuss with the project sponsor effectively. (Ref: The Standard for Risk Management Pg. 34)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago