exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 224 discussion

Actual exam question from PMI's PMI-RMP
Question #: 224
Topic #: 1
[All PMI-RMP Questions]

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

  • A. Ask the project sponsor for more budget to deal with this risk.
  • B. Revisit this risk in the risk register and redefine the mitigation strategy.
  • C. Mark this new risk as an extremely high priority and inform all stakeholders.
  • D. Activate the contingency plan to handle this risk during execution.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
4 weeks, 1 day ago
Selected Answer: D
When a mitigation strategy still leaves a substantial residual risk, the contingency plan should be activated to address the potential impact of the risk. The contingency plan is specifically designed to manage risks that remain after mitigation efforts.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago