A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

  • A. Communicate the latest status to the steering committee and provide a demo of the features completed.
  • B. Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.
  • C. Schedule routine demos on features completed and deliver a single product once all features are completed.
  • D. Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 5 days ago
Selected Answer: D
D. Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...