Question #: 1403
Topic #: 1
[All PMP Questions]

A project team is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

  • A. Use a market-based strategy.
  • B. Rely on the expert judgment of the product owner.
  • C. Perform collaborative work that is coordinated by the project manager.
  • D. Engage the project sponsor.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: C
C. Perform collaborative work that is coordinated by the project manager. option C is the best choice because it promotes collaboration among the team and ensures that the prioritization of product features is thorough, balanced, and customer-focused, while being coordinated effectively by the project manager.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: C
C. Perform collaborative work that is coordinated by the project manager
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...