Exam PMP topic 1 question 1406 discussion

Actual exam question from PMI's PMP
Question #: 1406
Topic #: 1
[All PMP Questions]

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management, since there is no project management office (PMO). The managers involved are unaware of their responsibilities for the project.

What should the project manager do?

  • A. Provide project management training to the stakeholders and explain their responsibilities.
  • B. Start planning the project and then request that a PMO be implemented in the organization.
  • C. Request that the implementation of a PMO be executed in parallel with the project.
  • D. Provide project management training to only the internal team involved in the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mengyaoyao
1 week, 4 days ago
Selected Answer: A
A. Provide project management training to the stakeholders and explain their responsibilities
upvoted 2 times
...
MonBouj
1 month ago
Selected Answer: C
C. Request that the implementation of a PMO be executed in parallel with the project. => Foundation for Best Practices Support for Project Execution Clear Roles and Responsibilities Long-Term Benefits Option C is the best choice as it addresses the root cause of the issues by establishing a PMO, ensuring that the project can be managed effectively with clear roles and guidelines from the outset.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: A
A. Provide project management training to the stakeholders and explain their responsibilities
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.