A project manager for a construction site realizes the importance of stakeholder relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

  • A. Assess the need to collaborate with the community.
  • B. Analyze the need to negotiate with the community.
  • C. Assess the information requirements of the community.
  • D. Analyze stakeholder diversity in the community.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month, 1 week ago
Selected Answer: C
C. Assess the information requirements of the community. This option focuses on understanding what information the local community needs, how they prefer to receive it, and the timing of that information. By assessing these requirements, the project manager can ensure that the engagement plan is tailored to effectively meet the community's needs and concerns, fostering a positive relationship. => Tailored Communication Building Trust Proactive Engagement While options A (collaboration), B (negotiation), and D (analyzing diversity) are also important considerations for stakeholder engagement, understanding the information needs is a critical foundational step that directly influences how effectively the project manager can engage and communicate with the community.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: C
C. Assess the information requirements of the community
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...