Actual exam question from PMI's PMP
Question #: 1396
Topic #: 1
[All PMP Questions]

A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project manager use as a guide to resolve the issue?

  • A. Project organization charts
  • B. Project charter
  • C. Stakeholder register
  • D. Team charter
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: D
D. Team charter Using the team charter as a guide allows the project manager to clarify roles and expectations, helping to resolve misunderstandings among team members and improving overall team productivity.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: D
D. Team charter
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted