Actual exam question from PMI's PMP
Question #: 1398
Topic #: 1
[All PMP Questions]

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two.)

  • A. Ask the team member to work overtime to make up the lime lost so that the project schedule is not impacted.
  • B. Log it in the risk register and work with the relevant owner to implement the mitigation action plan.
  • C. Analyze the impact of the issue and submit a change request to update the project schedule.
  • D. Inform the project sponsor that the risk has materialized and request that the project budget be increased.
  • E. Extend the project deadline and update the project schedule to reflect the delay.
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: BC
B. Log it in the risk register and work with the relevant owner to implement the mitigation action plan C. Analyze the impact of the issue and submit a change request to update the project schedule. Taking the appropriate actions of logging the risk in the risk register and analyzing its impact through a change request ensures that the project manager is addressing the materialized risk responsibly and systematically, paving the way for better project management practices in the future.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: BC
B. Log it in the risk register and work with the relevant owner to implement the mitigation action plan C. Analyze the impact of the issue and submit a change request to update the project schedule
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...