A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed one of the risks materialized and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

  • A. Risk occurred
  • B. Risk monitored
  • C. Risk managed
  • D. Risk identified
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: A
A. Risk occurred. The project manager moves a risk from the risk register to the issue log when the risk occurs. This transition signifies that the previously identified risk has materialized and requires immediate attention and resolution as an active issue in the project.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: A
A. Risk occurred
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...