Actual exam question from PMI's PMP
Question #: 1385
Topic #: 1
[All PMP Questions]

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests. Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders.

What document should the project manager use to communicate these requests?

  • A. Risk log
  • B. Backlog
  • C. Change log
  • D. Issue log
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: C
C. Change log The change log is the correct document to use for communicating the status of deferred change requests to stakeholders, as it ensures that changes are properly documented and tracked throughout the project.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: C
C. Change log
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...