Question #: 1375
Topic #: 1
[All PMP Questions]

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors.

What should the project manager do to ensure the successful execution of the project?

  • A. Oversee the selection process for the vendor to procure the needed products and services.
  • B. Ask the procurement department to select the vendor using established processes.
  • C. Activate the mitigation plan for the procurement risks.
  • D. Perform procurement control checks throughout the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: D
D. Perform procurement control checks throughout the project. Performing procurement control checks ensures continuous oversight of vendor performance and is critical to ensuring that the project remains on track during the execution phase.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: D
D. Perform procurement control checks throughout the project
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...