A project manager is assigned to lead a hybrid innovation project. During a meeting with the sponsor and major stakeholders, the project manager realizes that the requirements are unclear.
What should the project manager do in this situation?
A.
Request that the sponsor meet with the product owner to address the issue.
B.
Help the sponsor and major stakeholders to craft the product vision.
C.
Add this to the risk register and monitor the risk until this becomes an issue.
D.
Review lessons learned to see how sponsors deal with issues about unclear requirements.
B. Help the sponsor and major stakeholders to craft the product vision.
The project manager should actively facilitate the discussion rather than just pass the responsibility to others.
By choosing B, the project manager actively engages with the sponsor and stakeholders to establish a clear product vision, which is essential for guiding the project and ensuring that requirements are understood and agreed upon. This collaborative approach will help align everyone involved and set a solid foundation for the project's success.
B. Help the sponsor and major stakeholders to craft the product vision
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MonBouj
1 month agovictory108
1 month, 1 week ago