A new project manager is initiating a project and realizes the team members are all very rigid, unwilling to change, and constantly state that they have been running projects successfully for years. The project manager realizes that the project will be at risk if the team does not adopt an agile approach.
What should the project manager do?
MonBouj
1 month agovictory108
1 month, 1 week ago