Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1342 discussion

Actual exam question from PMI's PMP
Question #: 1342
Topic #: 1
[All PMP Questions]

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed. This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

  • A. Discuss project requirements with the new stakeholder, and update the communications management plan.
  • B. Send evidence to the new stakeholder that the project's status was sent according to the schedule.
  • C. Suggest that the new stakeholder review the project status before the next board meeting.
  • D. Share the communications management plan with the new stakeholder.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: A
A. Discuss project requirements with the new stakeholder, and update the communications management plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...