Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company's competitive advantage. What should the project manager do?
A.
Start the process to include the new features of the product on the next iteration.
B.
Allow all requested changes and bypass the company's change control process.
C.
Reject all requested changes and bypass the company's change control process.
D.
Encourage the project team to add premium features to impress the client.
A. Start the process to include the new features of the product on the next iteration
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.