Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1347 discussion

Actual exam question from PMI's PMP
Question #: 1347
Topic #: 1
[All PMP Questions]

A project sponsor asks the project team to add an enhancement to the project. How should the project manager address this request?

  • A. Accept the request because it came from the project sponsor.
  • B. Refuse the project sponsor’s request because it is out of scope.
  • C. Check if the budget can cover the enhancement.
  • D. Validate the proposed change's impact on the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: D
D. Validate the proposed change's impact on the project
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...