Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1338 discussion

Actual exam question from PMI's PMP
Question #: 1338
Topic #: 1
[All PMP Questions]

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided details to the customer 2 weeks ago and set up a weekly conference call to effectively communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

  • A. Request a change in the contract to include the shipment in the project management plan.
  • B. Find the root cause of the issue and discuss the customer's current engagement.
  • C. Inform the customer that subsequent packages cannot be manufactured.
  • D. Request a delivery date extension from the customer.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: B
B. Find the root cause of the issue and discuss the customer's current engagement
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...