An agile team has completed 9 out of 10 stories for the sprint. During the retrospective, a few team members pointed out that they finished all of their stories. However, one team member failed to finish a story.
What should the agile leader do?
A.
Emphasize to the team that each member is responsible for their story, but the team is collectively responsible for finishing the sprint.
B.
Suggest that the team assign stories at the beginning of the sprint based on each person's strengths to maximize performance.
C.
Work with the product owner to remove the story from the sprint because the points cannot be split.
D.
Ask the team to address this at the next sprint planning instead of at the retrospective.
A. Emphasize to the team that each member is responsible for their story, but the team is collectively responsible for finishing the sprint
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mgaidiwahid
1 month, 2 weeks agovictory108
1 month, 2 weeks ago