Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1326 discussion

Actual exam question from PMI's PMP
Question #: 1326
Topic #: 1
[All PMP Questions]

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

  • A. Request a cancellation of the procurement contract with the supplier and impose a penalty.
  • B. Review the procurement contract and ask the supplier to negotiate a solution.
  • C. Escalate this issue to senior management, as the supplier is not following the procurement contract.
  • D. Request a revision of the procurement contract to include specifications for the parts.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: B
B. Review the procurement contract and ask the supplier to negotiate a solution
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...