Exam PMP topic 1 question 1328 discussion

Actual exam question from PMI's PMP
Question #: 1328
Topic #: 1
[All PMP Questions]

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

  • A. Plan to hire more experienced team members and lay off a few of the existing team members.
  • B. Communicate the situation to the customer and inform them about potential delays in delivery.
  • C. Report the situation back to upper management and request to have the scope changed.
  • D. Communicate the situation to the team and plan for the necessary training and coaching arrangements.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: D
D. Communicate the situation to the team and plan for the necessary training and coaching arrangements
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted