Exam PMP topic 1 question 1311 discussion

Actual exam question from PMI's PMP
Question #: 1311
Topic #: 1
[All PMP Questions]

During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team.

What should the project manager do?

  • A. Request that the project team members learn the required domain knowledge and resolve the open issues in a short time.
  • B. Review the open issues with the issue reporter and issue a change request to hire an external domain expert.
  • C. Ask the issue reporter to close the issues, because there are no project team members who have the required domain knowledge.
  • D. Reduce the project scope to ensure that the project team has the knowledge to deliver the system on schedule.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: B
B. Review the open issues with the issue reporter and issue a change request to hire an external domain expert
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted