Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1307 discussion

Actual exam question from PMI's PMP
Question #: 1307
Topic #: 1
[All PMP Questions]

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

  • A. Add additional resources to the project to fast track certain activities and reduce delays.
  • B. Communicate the delay to stakeholders and maintain the existing budget baseline.
  • C. Evaluate the fallback plan proposed by the team and submit a change request, if required.
  • D. Use the existing budget for executing the fallback plan and update the baseline.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: C
C. Evaluate the fallback plan proposed by the team and submit a change request, if required
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...