During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
A.
Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP).
B.
Design a set of metrics including velocity, which is a good measure of value delivered.
C.
Promote a productive environment where everybody can work without interruptions from the rest of the team members.
D.
Create a reward system recognizing group contributions to get people motivated and improve performance.
A. Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 3 weeks ago