Question #: 1293
Topic #: 1
[All PMP Questions]

A lead project manager for an agile project needs to prioritize requirements, define the scope of the initial product, and deliver the approved scope in a series of multiple versions. What should the project manager do next?

  • A. Determine the expected benefits of each requirement to maximize the overall business value.
  • B. Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list.
  • C. Work with the product owner to evaluate and prioritize the requirements.
  • D. Prioritize the requirements based on the hierarchical level of the requesting stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Work with the product owner to evaluate and prioritize the requirements
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.