A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

  • A. Refer the lead project manager to the communications management plan.
  • B. Negotiate a mutually agreeable feedback cycle with acceptable timelines.
  • C. Update the communications management plan and the stakeholder engagement plan.
  • D. Escalate the issue to the functional manager and explain the situation to them.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: B
B. Negotiate a mutually agreeable feedback cycle with acceptable timelines
upvoted 1 times
...
Ngho
1 month, 3 weeks ago
B. Negotiate a mutually agreeable feedback cycle with acceptable timelines. Since both project managers are equal in seniority and report to the same functional manager, the most constructive approach is to directly address the communication issue by negotiating a clear feedback cycle that is acceptable to both parties. This will help establish boundaries and ensure that updates are provided at regular intervals without the need for constant, reactive requests. A negotiated agreement can help maintain a professional working relationship and avoid unnecessary escalation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.