Question #: 187
Topic #: 1
[All PMI-PBA Questions]

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s) versioning?

  • A. Project plan
  • B. Statement of work
  • C. Traceability matrix
  • D. Problem or opportunity statement
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ngunhucho
1 month, 3 weeks ago
Selected Answer: C
C. Traceability matrix 3. Requirements Traceability Matrix (RTM): Updating the Traceability Matrix: If a traceability matrix is being used, update it to reflect the changes in the requirements. This ensures that the modified requirement is still linked to corresponding design, development, and test cases. Version Tracking in RTM: The traceability matrix should reference the updated version numbers of the requirements to maintain clear visibility of the changes across the lifecycle.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...