Exam PMP topic 1 question 1286 discussion

Actual exam question from PMI's PMP
Question #: 1286
Topic #: 1
[All PMP Questions]

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

  • A. Request marketing to launch an advertising campaign for the product that is currently in stock.
  • B. Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.
  • C. Meet with the engineering team to manufacture the materials in-house.
  • D. Explore if the materials could be supplied locally and obtained on time.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: D
D. Explore if the materials could be supplied locally and obtained on time
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...