Actual exam question from PMI's PMP
Question #: 1288
Topic #: 1
[All PMP Questions]

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

  • A. Ask human resources (HR) to coordinate another activity.
  • B. Inform HR about the situation and ask for support.
  • C. Meet with the team to explain that conflicts must be addressed and solved.
  • D. Reassess the team situation and provide a proper solution.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: D
D. Reassess the team situation and provide a proper solution
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.