Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1289 discussion

Actual exam question from PMI's PMP
Question #: 1289
Topic #: 1
[All PMP Questions]

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

  • A. Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.
  • B. Replace poorly performing team members with more experienced members, setting an example of accountability for the team.
  • C. Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.
  • D. Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...