Question #: 1278
Topic #: 1
[All PMP Questions]

A project manager has recently joined a small company. The company's chief operating officer (COO) asked the team to skip some steps in the process in order to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.

What should the project manager do?

  • A. Redesign the process so the team can move more quickly.
  • B. Notify all team members that all steps in the process must be completed.
  • C. Schedule a review of the process steps with the team and the COO.
  • D. Escalate the issue to the other executive leadership members.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Schedule a review of the process steps with the team and the COO
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...