A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members on the team who have more experience with similar tasks.
What should the project manager do?
A.
Ask one of the more experienced team members to support the team member with the task.
B.
Ask the experienced team members to produce a manual on how to complete the task.
C.
Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.
D.
Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.
A) .This approach promotes collaboration and knowledge sharing within the team, helping the struggling team member improve their skills while also ensuring that the task is completed efficiently. It fosters a supportive team environment and encourages mentorship.
A. Ask one of the more experienced team members to support the team member with the task
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Seema_Na
1 month, 2 weeks agovictory108
6 months, 2 weeks ago