Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 390 discussion

Actual exam question from PMI's CAPM
Question #: 390
Topic #: 1
[All CAPM Questions]

A construction project is underway and there are three months left to complete the building. A public authority responsible for approving the final stage is stalling the project.

What should the project manager do?

  • A. Visit the public authority headquarters and formally petition them, demanding an explanation about this delay.
  • B. Mitigate the risk of missing the deadline by requesting an alternative public authority to participate in the approval process.
  • C. Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.
  • D. Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
RyeBread
1 month, 3 weeks ago
Selected Answer: C
C. Report the issue to major stakeholders and explore possible corrective actions along with legal assistance. Reporting the issue to major stakeholders ensures that all key parties are aware of the delay and can provide input on potential solutions. Exploring corrective actions and seeking legal assistance can help navigate the bureaucratic process and find ways to expedite the approval.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...