One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A.
Review and update the project ground rules to make meeting attendance mandatory.
B.
Assign this member to facilitate the next meeting to ensure project team collaboration.
C.
Understand the reason for the team member’s absence and encourage them to attend future meetings.
D.
Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.
C. Understand the reason for the team member’s absence and encourage them to attend future meetings
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 1 week ago