Exam PMP topic 1 question 1258 discussion

Actual exam question from PMI's PMP
Question #: 1258
Topic #: 1
[All PMP Questions]

A team member is openly criticized by others during a standup meeting for failing to complete yesterday's tasks. What should the agile coach do first to address the situation?

  • A. Avoid the discussion by referring to the team charter.
  • B. Let the discussion go on as it is important that the team is clear on priorities for the day.
  • C. Address the team members involved during the next sprint retrospective.
  • D. Emphasize the ground rules and then focus on today's activities and impediments.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: D
D. Emphasize the ground rules and then focus on today's activities and impediments
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...