Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1416 discussion

Actual exam question from PMI's PMP
Question #: 1416
Topic #: 1
[All PMP Questions]

A project requires testing of the final product to be done at another department’s testing facility, which is known for having low availability. This situation could potentially impact the project schedule.

What should the project manager do next?

  • A. Update the project schedule.
  • B. Update the issue log.
  • C. Update the lessons learned register.
  • D. Update the risk register.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: D
D. Update the risk register is the most appropriate next step because it allows the project manager to document and prepare for the potential risk to the project schedule, ensuring proactive risk management.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: D
D. Update the risk register
upvoted 1 times
...
prokat_mashin_na_vicecity
1 month, 3 weeks ago
Right answer is - Update Risk register cuz risk has not been realized. If already realized, then would be Update the issue log.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...