A project requires testing of the final product to be done at another department’s testing facility, which is known for having low availability. This situation could potentially impact the project schedule.
D. Update the risk register
is the most appropriate next step because it allows the project manager to document and prepare for the potential risk to the project schedule, ensuring proactive risk management.
Right answer is - Update Risk register cuz risk has not been realized. If already realized, then would be Update the issue log.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MonBouj
1 month agovictory108
1 month, 1 week agoprokat_mashin_na_vicecity
1 month, 3 weeks ago