Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1248 discussion

Actual exam question from PMI's PMP
Question #: 1248
Topic #: 1
[All PMP Questions]

A project with multiple teams recently transitioned from a predictive approach to agile as requested by the product owner. Midway through implementation, a team member noticed there was no technical capability to support the current business requirement; therefore, the project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

  • A. Requested the product owner's approval to add an external expert to define the acceptance criteria
  • B. Defined a clear acceptance criteria at the initiation phase and continued with the project
  • C. Assessed the technical and organizational readiness for the project and identified risks at the beginning of the first iteration
  • D. Increased the communications between the team member and the product owner
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Assessed the technical and organizational readiness for the project and identified risks at the beginning of the first iteration
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...