Actual exam question from PMI's PMP
Question #: 1249
Topic #: 1
[All PMP Questions]

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products. A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

  • A. Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework.
  • B. Define a ground rule to comply with the quality standard and ask the team members to apply it.
  • C. Understand the context and interdependencies of the process from the team members and then define improvements.
  • D. Continue with the process as is, and wait until the next phase to suggest any improvements.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: C
C. Understand the context and interdependencies of the process from the team members and then define improvements
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...