In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have most likely caused this communication breakdown?
A.
The daily standup meetings were not consistently attended.
B.
The weekly project status reports were not published regularly.
C.
The sprint review meetings were not held regularly.
D.
The project manager failed to develop a communications management plan.
A. The daily standup meetings were not consistently attended