Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1240 discussion

Actual exam question from PMI's PMP
Question #: 1240
Topic #: 1
[All PMP Questions]

A project manager is working on a project using a hybrid approach. The project is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company, which was approved by their functional manager.

What should the project manager do first in this situation?

  • A. Ask the functional manager for an immediate replacement for the team member.
  • B. Review the risk management plan and mitigation plan to understand the impact of this issue.
  • C. Ask the functional manager why a decision was made without consulting them.
  • D. Use soft skills to influence the team member to stay until the project is completed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: B
B. Review the risk management plan and mitigation plan to understand the impact of this issue
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...