Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1221 discussion

Actual exam question from PMI's PMP
Question #: 1221
Topic #: 1
[All PMP Questions]

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?

  • A. Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.
  • B. Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.
  • C. Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.
  • D. Ask the sponsor to start a new project to support the existing project and help it meet the original time line.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: A
A. Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...