Exam PMP topic 1 question 1226 discussion

Actual exam question from PMI's PMP
Question #: 1226
Topic #: 1
[All PMP Questions]

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway. Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

  • A. Propose a pause in this phase to save labor costs and asset depreciation.
  • B. Proceed with the project using management reserves to cover any delays or losses.
  • C. Establish new partnerships with other suppliers in anticipation of any delays.
  • D. Perform a risk assessment and define a risk response action plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: D
D. Perform a risk assessment and define a risk response action plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...