Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1228 discussion

Actual exam question from PMI's PMP
Question #: 1228
Topic #: 1
[All PMP Questions]

After a project team has been working on a project for several months, the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

  • A. Archive the project artifacts on the project manager's local computer for future reference.
  • B. Document the project sponsor's instructions as the archived project artifacts.
  • C. Comply with the project sponsor's request to not archive the project artifacts.
  • D. Consult with the project management office (PMO) for guidance on project artifacts.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: D
D. Consult with the project management office (PMO) for guidance on project artifacts
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...