Actual exam question from PMI's PMP
Question #: 1229
Topic #: 1
[All PMP Questions]

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

  • A. Refer to the project's resource management plan.
  • B. Ask the project sponsor for external resources.
  • C. Reschedule the project taking this new information into account.
  • D. Create a change request to be validated by the project sponsor.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: A
A. Refer to the project's resource management plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...