Question #: 1216
Topic #: 1
[All PMP Questions]

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated by other team members.

Which three actions should the project manager take? (Choose three.)

  • A. Identify the isolated team member as a risk and document the situation in the risk register.
  • B. Get feedback from other team members to understand what led to this situation.
  • C. Obtain feedback from the isolated team member to understand the situation.
  • D. Allow team members to resolve personal issues without involving the project manager.
  • E. Arrange and conduct team-building sessions to improve team effectiveness.
Show Suggested Answer Hide Answer
Suggested Answer: BCE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sarvesh_D
3 weeks, 4 days ago
Selected Answer: BCE
BCE is correct
upvoted 1 times
...
victory108
1 month, 3 weeks ago
Selected Answer: BCE
B. Get feedback from other team members to understand what led to this situation C. Obtain feedback from the isolated team member to understand the situation E. Arrange and conduct team-building sessions to improve team effectiveness
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...